Bitcoin mining companies have successively signed long-term contracts for AI data centers this year. Stock prices reached highs in May and June, and most of them fell back to the original point six months later. Based on Yahoo Finance's closing price, IREN closed at $12.85 on November 25, down 81% from its closing high of $67.84 on May 27; Cipher Digital also fell 81% from its high.

According to Chain News statistics, among the 9 listed mining companies that are transforming into AI, the decline of 8 from this year’s high is greater than Bitcoin’s 38%. Judging from the rise and fall this year, IREN, Cipher, CleanSpark, Galaxy and MARA have fallen more than 31% of Bitcoin; during the same period, the Nasdaq 100 ETF (QQQ) has increased slightly by 3%.

Stock prices of 9 mining companies compared to Bitcoin and QQQ

Company (code name) 11/25 Closing (USD) this year 2026 Closing High (Date) from high point IREN (IREN) 12.85 -66.0% 67.84 (5/27) -81.1% Cipher Digital (CIFR) 5.51 -62.7% 29.18 (6/18) -81.1% CleanSpark(CLSK) 5.18 -48.8% 18.81 (6/1) -72.5% Galaxy Digital (GLXY) 11.56 -48.3% 34.31 (1/16) -66.3% TeraWulf(WULF) 10.03 -12.7% 28.98 (6/18) -65.4% MARA (MARA) 5.42 -39.6% 14.85 (6/1) -63.5% Hut 8 (HUT) 48.83 +6.3% 133.02 (6/2) -63.3% Core Scientific(CORZ) 10.82 -25.7% 29.16 (6/18) -62.9% Riot Platforms (RIOT) 16.65 +31.4% 28.69 (6/23) -42.0% Bitcoin (BTC) 60,223 -31.2% 96,929 (1/14) -37.9% Nasdaq 100 ETF (QQQ) 633.93 +3.2% 759.66 (10/6) -16.6%

In the table, only Riot and Hut 8 are still rising this year. Riot is up 31% and is the only one that has fallen less than 50% from its high. Bitcoin price is Yahoo Finance Nov 25 daily line, highs are also based on closes as stocks.

The contract value can easily reach tens of billions of dollars, and most of the rent will not be paid until 2027.

The contracts held by these companies are quite large. TeraWulf announced in July that it had signed a 20-year lease with Anthropic for a Kentucky campus of approximately 401 MW, with estimated rental revenue of approximately US$19 billion. Google later financed the leaseProvide credit guarantee. according toTeraWulf Announcements, the first batch of production capacity will not come online until the second half of 2027, and will not be fully loaded until early 2028.

Hut 8 has signed two leases of 15 years each, 352 MW, and US$9.8 billion in Beacon Point Park, Texas. The lessee is an unnamed high-rated company. The company's AI data center contract has a total contract value of US$26.6 billion. butHut 8 third quarter financial resultsIt shows that the first data hall will not be delivered until the second quarter of 2027, and there is currently no rental income from the AI ​​data center.

Cipher's Barber Lake campus in Texas is leased by Fluidstack and guaranteed by Google. In September, it signed a second 10-year contract with a "leading AI laboratory", increasing the total contract value to approximately $9.1 billion. Two other campuses are leased to Amazon AWS for a combined total of about $7.5 billion. Cipher did not recognize its first HPC rental revenue until the third quarter.

IREN delivery delayed, $6 billion still to be raised

IREN is the company that has transformed the fastest. It signed a five-year, US$9.7 billion cloud service contract with Microsoft, and also signed a five-year, US$3.4 billion contract with Huida.IREN quarterly results released on November 5It shows that revenue from July to September was US$228 million, including US$200 million from the AI ​​cloud, which was nearly twice as much as the previous quarter, but it still had a net loss of US$263 million in a single quarter.

The same quarterly report also extended the target of "annualized revenue of more than $4 billion" from the end of 2026 to January 2027, and said it "may be extended to the end of February." Co-chief executive Daniel Roberts said the delay was due to "customer-required design changes and supplier schedules."

IREN still has $15 billion in capital expenditures to pay for this fiscal year, of which $9 billion has been covered by cash, GPU financing and customer prepayments, and the remaining $6 billion is listed as "target" financing, subject to "subject to market conditions." Microsoft also reported this month that it is re-examining its cooperation with Neocloud players such as IREN. Chain News previouslyReported relevant details。

The data center was built with debt and the issuance of new shares.

Most of the money for building a data center comes from bonds and issuance of new shares, and the interest rates are not low. Galaxy issued $3.507 billion in secured bonds in July for the second phase of its Helios campus in Texas,Coupon interest rate 9.875%, this phase of the park is fully leased to CoreWeave. IREN secured $2.4 billion in GPU financing at a fixed rate of 9% for non-investment-grade customer deployments; Core Scientific issued $3.3 billion of 7.75% secured bonds in April.

Equity dilution is also a common phenomenon. TeraWulf, which raised more than $1 billion in April by issuing 54.51 million shares at $19 each, ended the third quarter with total debt of $5.8 billion, $2.5 billion of which was convertible debt. IREN raised a total of about US$2.6 billion from new stock issuances in the second and third quarters, and issued another US$3 billion in convertible bonds in May. Cipher issued $850 million of zero-coupon convertible bonds in October.

You should also take a closer look at the profit figures on the financial reports. TeraWulf's net profit in the third quarter was approximately US$710 million and Core Scientific's approximately US$1.18 billion, mainly from non-cash changes in the fair value of warrants. The decline in stock prices actually increased book profits. Core Scientific had a net loss of $1.16 billion in the previous quarter due to the same change in warrant valuation.

Riot still rises 31% this year: selling Bitcoin, not increasing capital

Riot went the other way.Riot third quarter financial resultsIt shows that the company sold 20,264 Bitcoins this year in exchange for about US$1.5 billion, which was mainly used to build data centers. It did not issue any additional shares in 2026 and said it "currently does not expect" to issue new shares for announced projects.

On November 4, Riot signed a 910 MW, 15-year "power land" lease in Corsicana, Texas, with an unnamed cutting-edge AI laboratory, with a total contract value of approximately US$28 billion. Under this lease, the tenant purchases, owns and operates the computing equipment. Riot only provides the land, power facilities and base. The capital expenditure is about US$6 million per MW, which the company says is about half of that of building a Tier 3 data center.

Together with AMD's Rockdale lease with the same lab, Riot has signed 1,151 MW, about $38 billion in data center contracts and paid off a $200 million Coinbase Bitcoin mortgage in September. However, Riot’s data center revenue in the third quarter was only US$18.4 million, and most contracts will not start paying rent until 2027 or 2028.

Funds betting on the transformation of mining companies are also being withdrawn. Former OpenAI researcher Leopold Aschenbrenner’s Hedge Fund Season 3Mining company holdings almost cleared out, IREN's holdings fell by 94%, and Core Scientific and Riot sold out.

this article Mining companies’ transformation to AI wakes up from a half-year dream: IREN has fallen 81% from its high point, and most have fallen worse than Bitcoin first appeared in Chain News ABMedia。