Brussels (Belgium) (AFP) – Belgian authorities have announced that they have imposed on Google the suspension of the construction site of one of its large data centers currently planned in the south of Belgium, after an alert from the Greenpeace organization on a lack of permits.

Published on: 11/27/2026 - 1:29 p.m.

This is the "data center" under construction in a business park straddling three municipalities in the Charleroi region (south), on a former mining site of around 50 hectares.

The administration of the Walloon region confirmed to AFP on Friday that it had issued "an order to stop construction", due to the "illegal construction" of a three-hectare building in recent weeks on the site.

“We have noted a major infraction. A report will be sent to the public prosecutor’s office,” declared Nicolas Yernaux, spokesperson for the public administration of Wallonia.

He recognized that the French-speaking region had been alerted by the NGO Greenpeace, which supports a mobilization of opponents of the project.

On Wednesday, Greenpeace announced the launch of "an emergency procedure" after observing through drone images that the construction site had progressed significantly in November despite a lack of permits.

The Google project was launched following a building permit issued by the authorities in 2024.

An impacted river

But the imbroglio dates back to this year, with the American giant's request to be able to modify the terms of the initial permit and to expand the constructed area, according to Nicolas Yernaux.

The request also aimed to authorize a cooling system for computer installations using water taken from a river, the Sambre, while the project originally provided for air cooling.

Against a backdrop of citizen mobilization, the regional minister responsible for Infrastructure, François Desquesnes, ended up refusing the amending permit this summer.

The opponents, united in particular in the “Stop Data Center” collective, brandished the fact that the episode of severe drought experienced since the spring made it necessary to preserve the water of the Sambre as much as possible.

Google has taken legal action to contest this refusal and a hearing is scheduled for early January.

Depending on the region, work could continue while respecting the first permit, but not based on the requirements formulated in the permit modification request.

“They built the new building as if they had it, but they did not have it (this amended permit),” insisted Nicolas Yernaux.

“Energivores”

On Thursday, controllers from the Walloon administration came to the site to verbally notify Google representatives of the shutdown of the site, where some 300 workers were working.

Requested by AFP, the Google group could not immediately be reached.

The American giant's plans to build mega data centers to support its AI (artificial intelligence) ambitions have already been thwarted in several countries.

A month ago the Finnish police announced that they had opened a criminal investigation into the environmental impact of preparatory work carried out on a planned Google site in Muhos (northern Finland).

In Belgium, where the American group has been present for twenty years, it is investing billions of euros to develop several data centers, promising hundreds of job creations.

Greenpeace justified the mobilization against the Charleroi project - planned for the neighboring towns of Farciennes, Sambreville and Aiseau-Presles - by accusing these installations of being "energy-intensive" against a backdrop of global warming.

“The climate crisis will only worsen in our regions. In this context, the construction of energy-intensive behemoths cannot go under the radar,” warned the environmental defense organization.